Photos of construction at Baan Suan Mok
|
Steelwork for the padstones and the foundation pillars
|
|
Padstones are 25 cms thick and 120 cms wide, reinforced with 16 mm steel
|
|
Rebar for the ground beams tied into the rebar for the pillars
|
|
Shuttering in place, ready to pour the concrete for the ground beams
|
|
Ground beams completed
|
|
Pouring 12 cms of concrete on top of the floor slabs
|
|
The pillars are cast. All are 15 cm square,
except the two on the patio which are 20 cms round.
|
|
The welding team starting on the roof frame.
|
|
Start of the wall block work.
This is the 14 cm "big cavity block" for enhanced insulation.
|
|
The roof and the walls taking shape
|
|
It took 6 men 5 days to complete the roof construction
|
|
... and they did very good job too.
All the welds will now be cleaned and the whole construction repainted.
|
|
The roof tiling takes five days to complete ...
|
|
All done except the copings, and this roof looks very nice indeed!
|
|
Today they started on the carport roof
|
|
Ridge irons for the coping tiles
|
|
Routing and conduits for the electrical system
|
|
The kitchen archway
|
|
The roof is now complete and the facia board is mounted
|
|
Internal rendering finished and suspended ceiling work started
|
|
External rendering and decorative stone work in progress
|
|
Septic tank and soakaway system for the second bathroom.
There's another behind the house for the master bathroom and kitchen.
|
|
Gypsum board ceiling work in progress.
These boards have a reflective aluminium foil back for heat insulation.
|
|
8,000 litre underground freshwater tank under construction.
|
|
You can see it's a double-wall steel-reinforced construction,
similar to the way swimming pools are built.
|
|
Internal wall plastering in progress.
This work gives a very smooth surface, much better than the standard concrete render.
|
|
Adding the finishing touches to the stepped ceilings.
|
|
The water storage tank now has a smooth, rubberized concrete render
|
|
Plumbing first fix and pouring the bathroom floors
|
|
The master bathroom starts to take shape
|
|
... and the second bathroom too
|
|
The first coat of anti-fungal primer paint
|
|
The door and window frames arrive.
|
|
The first coat of surface paint applied
|
|
Door and window frames mounted
|
|
Tiling of the living room and bedrooms underway
|
|
and the bathrooms too
|
|
Preparation of the 50m road and the driveway to plot 2.
|
|
The roadway is now sanded, compacted, and the steel is in place
|
|
Pouring and spreading the concrete at the plot 2 end of the road
|
|
Pouring and spreading the concrete at the entrance to Baan Suan Mok
|
|
And smoothing the road surface
|
|
The furniture maker installing the windows
|
|
Drilling a hole for the transformer post
|
|
Erecting the post
|
|
Now ready for the transformer and connection to the grid
|
|
Bath installed in the mater bathroom, now ready for the granite tops
|
|
Bathroom two tiled completely and now ready for granite
|
|
The doors are looking very good.
We've chosen the lightest Thai redwood we can find
and given it a light teak stain and polish.
|
|
The windows are of the same wood, with brass fittings.
|
|
Fitting the glass
|
|
Fitting the skirting boards
|
|
Granite counter tops and sanitary ware fitted
|
|
The chief furniture maker preparing the window sills for stain
|
|
and the beautiful, shining result
|
|
Underground cables for electricty and telephone
being protected with a three inch layer of concrete.
|
|
Mounting the 3-phase connection and meter cabinet beside the transformer
|
|
Building the fitted kitchen
|
|
Woodwork now all done, ready for staining and polishing
|
|
Connecting the transformer
|
|
The retaining wall and concrete posts for the pickett fence
|
|
Granite work tops now fitted in the kitchen.
|
|